Project Milestones

Sept 2003:  Review Mission

June 2003:   1000th STW installed in CGISP

Sept - Oct 2002:   CGISP Mid-Term Review

Oct 5, 2001: Deprosc Nepal has signed a contract with CECI for Social Mobilization work in 37 VDCs of Rautahat District. According to the agreement 1100 STWs will be installed within the next four year period in this district.

July 16, 2001: Goldhap VDC in Jhapa Districts becomes the first subproject to complete 15 STW.

April 6, 2001: Nepal Rasta Bank approved Sahara Co-operative as a CGISP PFI to cover subprojects in Jhapa District.

February 23 - March 2, 2001:  Project Review Mission

February 2001:  First batch of shallow tubewells completed in Mrigaulia, Morang and Saranamati, Jhapa.

November 11 - 29, 2000:  Project Review Mission

May 24 - June 1, 2000:  Project Review Mission

November 25 - December 16, 1999:  Project Review Mission

March 3, 1999:  Loan Effectiveness Date

November 17, 1998:  Loan Agreement Signed

January 30 - February 5, 1999:  Loan Inception Mission

January 25, 1999:  MOU signed between CIDA and HMG for CGISP Technical Assistance

October 29, 1997:  Loan Negotiation